We've bought an older house that needs nearly everything done. Where do you start, and what order avoids redoing work?

2 Answers

The golden rule: work from the structure outwards and from the dirty jobs to the clean ones, so finished work isn't damaged by later trades.

A typical order:

  1. Plan and approvals: design, budget, engineering, permits
  2. Structural and safety: footings, restumping, roof, termite treatment, load-bearing changes
  3. Weatherproofing: roof, gutters, windows and external doors
  4. Services rough-in: electrical rewiring, plumbing, gas, data, heating and cooling ducting, while walls and ceilings are open
  5. Insulation, then walls and ceilings: plasterboard, sheeting, rendering
  6. Wet areas: waterproofing and tiling for bathrooms and laundries
  7. Kitchen and joinery
  8. Fit-off: power points, light fittings, tapware, appliances
  9. Painting
  10. Flooring last, then landscaping

If you can't afford it all at once, do the invisible essentials first (structure, roof, wiring, plumbing) even though they're less satisfying than a new kitchen. Our guide on [the order to hire your tradies in](/blogs/renovating-the-order-to-hire-your-tradies-in) has more detail.

0
Gagan Kohli

Living in the house while renovating? Do one wet area at a time, so you always have a working bathroom.