How long does a kitchen renovation take?
Luxivai· 0 views
We're planning a full kitchen renovation and need to know how long we'll be without a kitchen. What's realistic, and what causes delays?
We're planning a full kitchen renovation and need to know how long we'll be without a kitchen. What's realistic, and what causes delays?
A typical full kitchen renovation takes about 4–8 weeks on site once work starts, but the planning phase often takes longer than the build.
Rough timeline:
Common causes of delay: late changes to the design, appliance or tile delivery delays, waiting for the stone benchtop, and surprises behind walls (old wiring, leaks).
Set up a temporary kitchen with a microwave, kettle, toaster and a sink in the laundry. It makes the weeks much easier.
Order the appliances early, and have them delivered before the cabinets are finished. Cabinet makers need the exact models to set the openings.