A typical full kitchen renovation takes about 4–8 weeks on site once work starts, but the planning phase often takes longer than the build.

Rough timeline:

  1. Design and selections: 2–6 weeks (layout, cabinetry, benchtops, appliances)
  2. Cabinet manufacture: often 3–6 weeks after final measure, which runs in parallel with planning
  3. On site:
  • Demolition: 1–2 days
  • Plumbing and electrical rough-in: 2–4 days
  • Plastering and repairs: 3–5 days
  • Cabinet installation: 2–4 days
  • Benchtop template, then manufacture: often 1–3 weeks for stone (the most common wait)
  • Splashback, appliances and fit-off: 3–5 days
  • Painting and touch-ups: 2–3 days

Common causes of delay: late changes to the design, appliance or tile delivery delays, waiting for the stone benchtop, and surprises behind walls (old wiring, leaks).

Set up a temporary kitchen with a microwave, kettle, toaster and a sink in the laundry. It makes the weeks much easier.

0
Gagan Kohli

Order the appliances early, and have them delivered before the cabinets are finished. Cabinet makers need the exact models to set the openings.