A progress payment is a payment made when the builder reaches a defined stage of the work, rather than paying everything at the start or the end. It matches what you pay to what's been built.

Typical stages for building work:

  1. Deposit (capped by law in most states)
  2. Base: slab or footings complete
  3. Frame: wall and roof frames complete
  4. Lock-up: external walls, roof, windows and doors in
  5. Fixing: internal linings, cabinets, doors and fittings
  6. Practical completion: the work is finished apart from minor defects

How to handle them:

  • Pay only when the stage is actually complete. Inspect it, or have an independent inspector check it on larger builds.
  • Make sure each claim matches the contract and any approved variations.
  • Some states set maximum percentages per stage for standard contracts.
  • Keep a record of every payment and invoice.

If you're financing the build, your lender usually releases funds per stage after their own valuation, so coordinate claim dates with the bank.